The time schedule for various activities will be as follows.
FOR MORE DETAILS CLICK;
1 Enquiries regarding installments/dues 5 working days
2 Mortgage permission18 working days
3 No Dues Certificate18 working days
4Conveyance Deed18 working days
5Transfer permission 18 working days
6Final Transfer5 working days
7DPC Certificate8 working days
8Possession Certificate7 working days
9Demarcation plan3 working days
10Sanction of Building Plan25 working days
11Completion Certificate
12 working days 12Refund10 working days
13Water/Sewerage connection12 working days